|
PIPE INSTALLATION
Extremely reliable and satisfactory installations
can be achieved without difficulty using PRINCE
u.PVC Pipes. Provided the special properties of this
material are fully understood and taken into
account. These are the most important factors to
consider.
(a) Due allowance must be made for the co-efficient
of thermal expansion
(b) Pipe work must be given adequate support,
particularly in respect of heavy
fitting.
(c) In the design of special components, abrupt
changes in cross section must
be avoided, since the material is notch - sensitive.
PRINCE Pipes are generally laid with the crown about
one meter below the surface. Allowance is to be made
for the relatively high co-efficient expansion of
PVC, particularly when laying on a hot day. Such
pipes should be allowed to cool off in the trench
before making the final connections and completing
the backfill. Air release valves should be
incorporated at all high points. These values may be
screwed into saddles, which can be used for ferrules
for service connection. Valves and other heavy
fittings should be properly anchored.
EXCAVATION The
trench should not be opened too far in advance of
pipe laying and should be backfilled as soon as
possible. The width of the trench at the crown of
the pipe should be as narrow as practicable, but not
less than the outside diameter of the pipe plus 300
mm (12 in.) to allow proper compaction of the side
fill. Above the crown of the pipe the trench may be
of any convenient width.
The trench should be excavated to the depth below
the invert of the pipe will allow necessary bedding.
Before placing this bedding, the trench bottom
should be prepared. All soft spots should be
hardened in by gravel or broken stone. Rock
projections should be removed. In fine grained soils
such clays, silts or fine sand, disturbance and
erosion of the bottom of the trench should be
prevented by placing a layer of bedding material 75
mm (3 in) thick on the virgin surface on the bottom
before permitting traffic.
MATERIAL FOR BEDDING AND SIDE-FILL
Clay should never be used immediately around the
pipe, for bedding, sidefill or backfill. It is not
possible to compact it sufficiently, and it is
liable to swell, shrink and erode.
Some other soils, however, as excavated from the
trench (such as free draining coarse sand, gravel,
loam and soils of friable nature)•may be suitable,
but must be capable of being compacted sufficiently
to provide support for the pipe. Fills such as hard
chalk, which break up when wet, should not be used.
Should the material excavated from trench be
unsuitable, then granular material must be imported.
The most suitable is gravel or broken stone from 10
mm to 5 mm (3/8 to 3/16) in size, since it requires
little tamping, but coarse sand, or sand and gravel
from 20 mm (3/4 in) down as it comes from the
quarry, is acceptable. An excess of fine particles
makes the mixtures more difficult compact when damp.
BEDDING AND SIDE FILLING
With flexible pipes it is of great importance that
the side fill should be very firmly compacted
between the sides of the pipe and the soil sides of
the trench sheeting should be partially withdrawn to
allow this to be done. Before backfilling ,any
leveling pegs or temporary packing should be
removed. The thickness of the bedding under the
barrel of the pipe should not be less than one-third
of the diameter, and a minimum of 100 mm. (4 in)
thick. In very soft or wet conditions or where the
bottom of the trench is very irregular, this
thickness should be increased as necessary, to give
a suitable bed.
The bedding should be thoroughly compacted in layers
not more than 150 mm. (6 in) thick to give a uniform
bed, true to gradient, on which the pipe may be
laid. Pipes should be laid directly on this bedding.
Bricks or other hard material must not be placed
under the pipes for temporary support. After the
pipes have been laid and tested. further bedding
material should be placed around the pipe and
thoroughly compacted in 75 mm. (3 in) layers by
careful tamping up to the crown of the pipe,
eliminating all cavities under the two lower
quadrants of the pipe.
The same material should then be placed over the
crown of the pipe for not less than two-third of the
diameter, with a minimum height of 100 mm. (4 in)
and a maximum of 300 mm. (12 in) and be thoroughly
compacted. The process of filling and tamping should
proceed equally on either side of the pipe, so as to
maintain an equal pressure on both sides.
BACK
FILLING Normal
filling of the trench should then proceed in layers
not exceeding 300 mm. (12 in) in thickness, each
layer being well rammed. Heavy mechanical rammers
should not be used until the fill has reached a
depth of 300 mm. (12 in) above the top of the pipe.
Special consideration and selection of backfilling
material will be necessary if the risk of surface
subsidence is an important consideration: for
example, tinder roads.
USE OF
CONCRETE SPECIAL CASES
Generally, the use of concrete with PVC pipes is
wasteful, since it converts a flexible pipeline into
a beam of negligible flexural strength, which will
fracture under minor ground movement. More than 2
Ft. of coyer concrete is normally unnecessary.
Less than 450 mm. (18 in) of cover, elsewhere than
under roads, narrow concrete slabs on a cushion of
filling material above the pipe should be used as a
protection against picks, etc. At shallow depths
under roads, etc, special consideration should be
given to all the engineering factors involved, such
as the class of roads, its construction, and the
proximity of other services.
At or above ground level concrete surround should be
used to protect the pipe.
|